Almonty reached the decisive operating milestones at Sangdong in the third quarter. On 17 September 2026, the company received the final certificates required to commercially operate the processing plant. The plant produced its first tungsten concentrate in September, the first at the site since 1993, and the first export cargo was loaded at the port of Busan in October. However, Sangdong contributed only C$0.1m of revenue in Q3, and the plant remains in commissioning and ramp-up during Q4 2026. Management has acknowledged technical challenges, and the equipment supplier is supporting Almonty’s operators on site. We therefore shift our Sangdong volume profile back by around three quarters.